Category: Tech

Wall insulation installed

HomeLab: Server Room Build – PT7 – Insulation time!

Well, with the intention of a full day on Sunday to get the external insulation installed and plasterboard all done, I slept until lunch time, bugger! Apparently I pushed a bit too hard on Saturday,

Server Room plaster board installed 01

HomeLab: Server Room Build – PT6 – Plasterboard time!

Early start Saturday morning I headed off to pick up some the hot aisle door & plasterboard sheets to get to work on the Server Room walls and ceiling. In lovely Australian fashion the temp

Lab No. 1

HomeLab: Let’s go back to the Start. Lab No. 1.

Well, as I have been hard at work and not had a chance to do anything with the Lab Build, I figure I should still post something in case someone is reading, lets lets take

Server Room Framing done pic 2

HomeLab: Server Room Build – PT5 – Framing done!

Over the weekend with a bit of commitment I managed to get the Server Room Framing done. Unfortunately I was a little challenged by some mildly to highly bowed wood but nothing a bit of

Server room Framing Photo

HomeLab: Server Room Build – PT4 – Framing time!

Yesterday I made a decent dent of progress on the Server Room Hot/Cold isle framing, being slightly challenged by the rubbish bowed wood I purchase I managed to get through pretty successfully. The rack looks